Projects
Lump Sum Turn Key (LSTK) Project to recover the flared gas at Uthmaniyah and Shedgum Aramco Gas Plants. The Project includes the development of complete detail engineering, the procurement of all materials, other than FGRS and Nitrogen Generation Units provided directly by Saudi Aramco, and all required civil, structural, mechanical, piping electrical, communication instrumentation and control systems works for the installation of the FGRS and the Nitrogen Generation Units.
In each plant the following will be installed:
- A Flaring Gas Recovery System (FGRS)
- A new Nitrogen Generator Unit (NGU)
- A new Flare Injection Pilot System
Scope of work
Engineering, Procurement, Construction
Period
2009 - 2010
Amount
€ 20,000,000