Mellitah Complex total shut down 2010

 
Mellitah_SD_2010_1

Performance:
• Total shut down scheduled in 10 days, delivered to Client 2 days ahead
• Safety score: Zero LTI
• During the preparation phase, additional work requests were received by the Operator, requiring the Contractor to review the plan (Shut down 2010 Additional Plan) in which all required additional extra were included

The project plan covered maintenance and inspection of 24 vessels (with internal scaffolding for 20 vessels, 2 critical vessels: off spec. condensate tank and flare k.o. drum) and electrical and instrumental maintenance activities.

Furthermore, during the execution phase, the Production Department required to perform some unplanned activities.

 

 

Scope of work
Total shut down