Project Highlights:
• Activities carried out in a brown field running at 550 bars, high percentage of H2S (5%)
• Pressurized environment for hot works in high risk areas
• Breathing apparatus for works performed on pipe rack above 4 metres
• Hydro-testing F22 spools at 908 bars
• Work performed 24/7 in difficult conditions (+45°C to -40°C)
• Total man-hours: 2,800,000
• Average (direct): 300 people (> 600 in peak period)
Performance:
• All 3 shut downs performed in 241 days, 31 days ahead of schedule (equivalent to 12% of total scheduling)
• Safety score: Zero LTI
Scope of work
replacement in 2009/2010 of 3 gas compressor trains piping system (X60/A333 material) with F22 material - installation and commissioning of new piping system, largemedium bore and high wall thickness (99mm)