The GMS covers a large area including but not limited to the main Plant in Nafoora (NGL) and 3 satellites GOSP (Nakla, Hamid, Tuama), various Utilities, trunk lines and flow lines to connect the wells, Power generation Plants (Turbo generators, Gas & Diesel Engines).
The Contract was relevant to Maintenance, Modifications, Upgrade & Revamping activities on the basis of an open contract (unit rates). The average people mobilized on site during the years is about 200 people, with picks of additional personnel during Shut Down. In Attachment 2, a brief description of the facilities (camp, offices, warehouse, workshop and main equipments) installed in the area and dedicated to manage the Contract.
During yearly Shut Down/T&I the activities included washing of tanks, vessel, spheroid, columns.
Scope of work
General Maintenance
Period
1999 - ongoing
Amount
€ 8,000,000/year