Early Gas Injection – Temporary Station of Bordolano – Phase 1-2-3

 
Bordolano_1

Phase 1 – Plant Implementation

Engineering, supply of materials, construction, commissioning and start-up of a Gas Compression Station (early injection) for underground storage activities. Besides the Contract includes management and operation of the compression station for a minimum period of 2 years. The plant includes:

  • two gas Moto compressor groups for gas injection
  • two diesel Moto generators Perkins 380-415V, 50 Hz 500KVA
  • all necessary auxiliary facilities such as: gas filter system, gas cooling system and flaring

Phase 1 Contract Period: started on 2008 will be completed on September 2009

Phase 1 value: € 14,000,000

 

 

Phase 2 – Plant Operation

Full Operation & Maintenance of the Station to storage natural gas from the existing distribution network to the Bordolano reservoir.

The Operation & Maintenance contract includes:

  • Smoth and continuous station running trough a dedicated team;
  • Maintenance engineering, spare parts management and activities schedule with the aim of CMMS system, implemented and installed for the scope of work;
  • Planned and unplanned maintenance interventions performed by a dedicated maintenance crew.

Phase 2 Contract period: from September 2009 to September 2011

Phase 2 value: € 11,800,000

 

 

Phase 3 – Plant Decommissioning

Plant will be decommissioned and disassembled for further relocation after the operational period.

Phase 3 value: € 2,368,000

 

 

 

Scope of work
Engineering, Procurement, Construction, Commissioning, Start-up, Operation, Maintenance, Decommissioning, Disassembling

Period
2008-2011

Amount
€ 28,168,000