Projects
Phase 1 – Plant Implementation
Engineering, supply of materials, construction, commissioning and start-up of a Gas Compression Station (early injection) for underground storage activities. Besides the Contract includes management and operation of the compression station for a minimum period of 2 years. The plant includes:
- two gas Moto compressor groups for gas injection
- two diesel Moto generators Perkins 380-415V, 50 Hz 500KVA
- all necessary auxiliary facilities such as: gas filter system, gas cooling system and flaring
Phase 1 Contract Period: started on 2008 will be completed on September 2009
Phase 1 value: € 14,000,000
Phase 2 – Plant Operation
Full Operation & Maintenance of the Station to storage natural gas from the existing distribution network to the Bordolano reservoir.
The Operation & Maintenance contract includes:
- Smoth and continuous station running trough a dedicated team;
- Maintenance engineering, spare parts management and activities schedule with the aim of CMMS system, implemented and installed for the scope of work;
- Planned and unplanned maintenance interventions performed by a dedicated maintenance crew.
Phase 2 Contract period: from September 2009 to September 2011
Phase 2 value: € 11,800,000
Phase 3 – Plant Decommissioning
Plant will be decommissioned and disassembled for further relocation after the operational period.
Phase 3 value: € 2,368,000
Scope of work
Engineering, Procurement, Construction, Commissioning, Start-up, Operation, Maintenance, Decommissioning, Disassembling
Period
2008-2011
Amount
€ 28,168,000
Related Images
| |
|
|
| |
|
|
| |
|
|
| |
|
|